Construction projects across the north west
At Buildmain Ltd in Manchester, we’re proud of what we can do! Take a look at some of our completed work, then get in touch. If you have any questions, check our FAQs or call the team.
Quality work on every project

Client: Outreach Community & Residential Services
H & S: site managers
Value: £100,500
Duration: 8 weeks
Summary:
-
1st floor phase 1 fit out refurbishment to create new office space and community facilities.
-
Pre-start meeting and provide all RAMS.
-
Isolate all services, strip and remove existing welfare and all partition ready to take new.
-
Remove existing window and supply and fit new, mechanically cut out pre-cast concrete.
-
Remove staircase, supply and fit new timber staircase as per drawing along with required hand rail
-
Supply and fit new partition and suspended ceilings as per drawing to create new lay out and office and welfare areas.
-
Fit new architraves door liners with fire doors and ironmongery to suit.
-
Tape and joint all partition as required and decorate.
-
Supply and fit new kitchen of required lay out with all appliances requested.
-
Upgrade plumbing and supply and plumb new combi boiler and required radiators with TVRs and all associated pipework - alterations made to drainage to accommodate new lay out.
-
DDA supply and fit Doc M pack with required toilet pan and all associated pipework, along with shower and small cloak room sink.
-
Create wet floor area to accommodate shower with shower bar and mixer tap.
-
Tile all welfare areas and kitchen splash back.
-
Electrical work - supply and install a new lay out, including sockets, LED lights, Cat 5 data points, emergency lighting and fire alarm.
-
Fit intercom system along with required telephone points.
-
Make new entrance door opening, supply and fit new entrance doors and fit all new required ironmongery.
-
Lay carpet tiles in required areas.
Works were completed within budget and on time.
Before and during the work
After

Client: Loreto Sixth Form College
H & S: site managers
Value: £7,500
Duration: 2 weeks
Summary:
-
Concrete hardstanding and drainage works.
-
Preliminaries and travel.
-
Pre-start meeting.
-
Provide RAMS for all work activities
-
Cordon off work area at the top and bottom of site.
-
Mechanically cut down existing trees as required.
-
Mechanically excavate trench using 3 ton machine approx. 300(d) x 30600(l) x 3200/4500(w)
-
Supply and lay 100mm of class 1 MOT.
-
Supply and lay 200mm square edge concrete edgings to match existing to the rear of the proposed slab.
-
Supply and lay 1200s DPM
-
Supply and fix 1 layer of A393 reinforcing steel mesh.
-
Install shuttering for expansion joints.
-
Supply and lay 35 gauge concrete - approx. 180 x 4500 x 3200/4500mm (approx. 120M2 (21.2M3)).
-
Allowance made for 15mm expansion joints, slab laid in 3 sections.
-
Agitated with vibrating poker.
-
Float and brush to a finish.
-
Excavate trench for drainage works - 2000 x 150 x 150mm.
-
Supply and lay A15 100mm channel drain set in gauged concrete.
-
Make good any effected surfaces.
Before
During and after work
Client: Laltex Group Leigh
Value: £60,000+
Project: security lodge demolition and reinstatement works
Summary:
-
Site survey.
-
Full H&S package.
-
Pre-start meeting.
-
Regular consultation meetings.
-
Site set-up.
-
Isolation of services.
-
Strip out.
-
Demolition of security office.
-
Break out of existing traffic island.
-
Reinstatement works of traffic island.
-
Block paving.
-
Install of automatic traffic barrier system.
-
Electrical works.
-
Landscaping.
-
Removal of all debris.
-
Clean and hand over.